  1. Apply wall covering above and below the Wall Box.

    240715-Hatch_Tiled-Apply_Wall_Material.eps
  2. Raise the floor until it is level with the flange on the drain unit.

    191119_Remote_pre_inst_raise_floor.eps
  3. Form a steep inclination towards the drain unit according to industry rules (min. 2% inclination). Make sure that the lowest part of the inclination is level towards the drain unit surface.